An overview of fish passage tests conducted with PNNL at our hydropower plant in Monroe, Oregon in the fall of 2020.

Turbine: 190cm diameter RHT at 5m head, 130 rpm
Quantity: 60 treatment, 59 control releases
Species: Rainbow trout, 200-400 mm length
Results: 100% immediate and 48h survival of turbine-passed fish

For more information on our fish passage testing, please visit https://www.natelenergy.com/fish-passage.

More Stories

Newsletters

Preserving Freshwater Ecosystems & Tripling Renewables — With Hydropower

While waterpower and conservation have had a fraught historical relationship, there is movement to align around the common goal of combating climate change.

Press

Modernizing Hydropower with Efficient, FishSafe Turbines: Natel in OWA's 2022 Year in Review

Read Abe Schneider's opinion piece in The Ontario Waterpower Association's 2022 Year in Review about why Canada needs hydro turbines that are safe for fish to pass through.

Newsletters

Natel Energy Winter 2023 Newsletter

What eels really want for Christmas, FishSafe™ turbines in the EU, freshwater conservation and 3X renewables united by hydropower. Our last update of 2023.