Video: Monroe Fish Passage Testing

December 9, 2020

An overview of fish passage tests conducted with PNNL at our hydropower plant in Monroe, Oregon in the fall of 2020.

Turbine: 190cm diameter RHT at 5m head, 130 rpm
Quantity: 60 treatment, 59 control releases
Species: Rainbow trout, 200-400 mm length
Results: 100% immediate and 48h survival of turbine-passed fish

For more information on our fish passage testing, please visit https://www.natelenergy.com/fish-passage.

More Stories

Announcements

Natel's Hydro Turbine Technology Could Help Reverse Decline of Atlantic Coast River Herring, New Study Suggests

A new study published in the North American Journal of Fisheries Management shows safe downstream passage of juvenile alewife (river herring) through Natel’s modern FishSafe hydro turbine.

Newsletters

Natel Energy Summer 2023 Newsletter

FishSafe turbines for higher head sites, a brighter future for Atlantic herring, Gia shares how to build more hydro, sustainably.

Press

WPTO checks in with the winners of the Fish Protection Prize

Natel's Center Sender, which uses electricity to guide fish more safely through or around turbines, was one of three winners of the 2020 Fish Protection Prize.